Fence Post Concrete Calculator
Concrete for a run of fence posts from hole diameter, depth and post count, waste included.
Each hole is pi times half the diameter squared times the depth, and the page multiplies by the post count and your waste percentage. A 20 kg bag is taken to yield about 0.01 cubic metres, in metric units.
A zero or negative diameter, depth or post count is refused by name. The post itself is not deducted from the hole volume, which the page states, so the figure is an over-estimate rather than a shortfall.
Every figure is an ordering estimate, not a structural specification, and none of it replaces an engineer's take-off. The arithmetic runs in your browser: nothing is uploaded and nothing is stored, so the same input prints the same answer on every reload.
Each hole is π × (diameter ÷ 2)² × depth, and the page multiplies by the post count and your waste percentage. A 0.3 m hole 0.9 m deep across six posts at 10 percent reads 0.42 m³, which is about 42 bags at the 20 kg yield of roughly 0.01 m³ per bag; units are metric.
Metric concrete per post run, from hole size, depth and post count.
An ordering estimate, not a structural specification.
How to use it
Enter hole diameter and depth in metres and the number of posts, set a waste percentage and press Run. The page prints the volume per hole, the run total, the total with waste and the bag count.
Waste and units
Each hole is a cylinder, so π r² is multiplied by depth once per hole and the post count scales it. The 20 kg bag yield of about 0.01 m³ is a nominal figure — bagged mixes differ — and it is printed so the bag count can be checked against the bag you actually buy.
Where the page stops
A zero or negative diameter, depth or post count is refused by name. The post itself is not deducted from the hole volume, so the figure is an over-estimate rather than a shortfall, and the page states that; ground conditions and a wider bell at the base are outside what it can see.
What to Expect
Best for
- Ordering bagged concrete for a post run.
- Seeing the volume per hole and the bag count together.
What this tool keeps
- The per-hole volume and the bag yield both print, so the count can be rechecked against another bag size.
What may need cleanup
- Nothing: the volumes and the bag count are the whole output.
Sample input
6 posts, 0.3 m diameter, 0.9 m deep, 10 percent waste
Sample output
Per hole: π × 0.15² × 0.9 = 0.0636 m³ 6 posts: 0.3817 m³ With 10 percent: 0.42 m³ ≈ 42 bags of 20 kg
Frequently asked questions
How much concrete per fence post?
Enter hole diameter and depth in metres and the post count, set a waste percentage and press Run. The page prints the per-hole volume, the run total and the bag count.
Is anything uploaded?
No. The cylinder volume is computed in this tab, so nothing is sent and nothing is stored.
Is the post volume deducted?
No. The page states that the post is not subtracted from the hole, so the figure is an over-estimate rather than a shortfall.
Is this a structural specification?
Every figure here is an ordering estimate, not a structural specification: it sizes a purchase, and an engineer's take-off or the manufacturer's data governs what is actually built.
Build custom tools for your store
Join the SDK program to create useful ecommerce utilities for your store.